46 C.F.R. § 31.01-20
Application for inspection of a new tank vessel or conversion of a vessel to a tank vessel—TB/ALL.
Cite as 46 C.F.R. § 31.01-20 (2026)
Prior to the commencement of the construction of any new tank vessel, or prior to the commencement of the conversion of any vessel to a tank vessel, application for the approval of contract plans and specifications and for a certificate of inspection shall be made in writing to the Coast Guard and no such construction or conversion shall be proceeded with until such approval is granted. (See § 31.10-1.)
- Cross-references to the CFR
- 31.10-1.