48 C.F.R. § 1436.270-2
Part I—The Schedule.
Cite as 48 C.F.R. § 1436.270-2 (2026)
The CO shall prepare the Schedule as follows:
(a)
Section A, Solicitation/contract form.
Use SF 1442, Solicitation, Offer, and Award (Construction, Alteration or Repair), as prescribed in FAR 36.701(a).
(b)
Section B, Bid schedule.
Bid schedule.
(c)
Section C, Specifications/Drawings.
Include specifications and drawings (
See
FAR Part 11) or reference other location in the uniform contract format (
e.g.
Section J, attachment ______).
(d)
Section D, Packaging and Marking.
Not applicable.
(e)
Section E, Inspection and acceptance.
Include inspection, acceptance, quality assurance, and reliability requirements (
See
FAR Part 46).
(f)
Section F, Deliveries or performance.
Include Suspension of Work, Liquidated Damages, Commencement, Prosecution, and Completion of Work, Variation in Quantity clauses (
See
FAR Part 12).
(g)
Section G, Contract administration data.
Include Contracting Officer's Representative/Technical Representative identification, and any required administration information (
e.g.,
accounting and appropriation data).
(h)
Section H, Special contract requirements.
Include any special contract requirements which are not included in other sections of the uniform contract format.