48 C.F.R. § 1843.205

Contract clauses.

Last amended: 2016Year: 2026Length: 60 wordsOfficial source

Cite as 48 C.F.R. § 1843.205 (2026)

As authorized in the prefaces of clauses FAR 52.243-1, Changes—Fixed Price; FAR 52.243-2, Changes—Cost Reimbursement; and FAR 52.243-4, Changes; and in the prescription at 43.205(c) for FAR 52.243-3, Changes—Time-and-Material or Labor-Hours, the period within which a contractor must assert its right to an equitable adjustment may be varied not to exceed 60 calendar days. [65 FR 58932, Oct. 3, 2000]