48 C.F.R. § 205.205-70
Notification of bundling of DoD contracts.
Cite as 48 C.F.R. § 205.205-70 (2026)
(a) When a proposed acquisition is funded entirely using DoD funds and potentially involves bundling, the contracting officer shall, at least 30 days prior to the release of a solicitation or 30 days prior to placing an order without a solicitation, publish in the Governmentwide point of entry (
https://www.sam.gov
) a notification of the intent to bundle the requirement. In addition, if the agency has determined that measurably substantial benefits are expected to be derived as a result of bundling, the notification shall include a brief description of those benefits (
see
FAR 7.107).
(b) This requirement is in addition to the notification requirements at FAR 10.001(c)(2)(i) and (ii).
[75 FR 40716, July 13, 2010, as amended at 88 FR 88533, Dec. 22, 2023]