48 C.F.R. § 22.1014

Delay over 60 days in bid opening or commencement of work.

Last amended: 2017Year: 2026Length: 94 wordsOfficial source

Cite as 48 C.F.R. § 22.1014 (2026)

If a wage determination was obtained through the e98 process, and bid opening, or commencement of work under a negotiated contract has been delayed, for whatever reason, more than 60 days from the date indicated on the previously submitted e98, the contracting officer shall submit a new e98. Any revision of a wage determination received by the contracting agency as a result of that communication shall supersede the earlier response as the wage determination applicable to the particular acquisition subject to the time frames in 22.1012-1(b) and (c). [71 FR 36935, June 28, 2006]