48 C.F.R. § 42.1302

Suspension of work.

Last amended: 2017Year: 2026Length: 44 wordsOfficial source

Cite as 48 C.F.R. § 42.1302 (2026)

A suspension of work under a construction or architect-engineer contract may be ordered by the contracting officer for a reasonable period of time. If the suspension is unreasonable, the contractor may submit a written claim for increases in the cost of performance, excluding profit.