48 C.F.R. § 817.7003

Policy.

Last amended: 2019Year: 2026Length: 57 wordsSubsections: 2Official source

Cite as 48 C.F.R. § 817.7003 (2026)

Undefinitized contract actions shall— (a) Be used only when— (1) The negotiation of a definitive contract action is not possible in sufficient time to meet the Government's requirements; and (2) The Government's interest demands that the contractor be given a binding commitment so that contract performance can begin immediately. (b) Be as complete and definite as practicable.
48 C.F.R. § 817.7003: Policy. | Justis AI