48 C.F.R. § 9.106-2
Requests for preaward surveys.
Cite as 48 C.F.R. § 9.106-2 (2026)
The contracting officer's request to the surveying activity (Preaward Survey of Prospective Contractor (General), SF 1403) shall— (a) Identify additional factors about which information is needed; (b) Include the complete solicitation package (unless it has previously been furnished), and any information indicating prior unsatisfactory performance by the prospective contractor; (c) State whether the contracting office will participate in the survey; (d) Specify the date by which the report is required. This date should be consistent with the scope of the survey requested and normally shall allow at least 7 working days to conduct the survey; and (e) When appropriate, limit the scope of the survey.