49 C.F.R. § 194.7

Operating restrictions and interim operating authorization.

Last amended: 2016Year: 2026Length: 113 wordsSubsections: 3Official source

Cite as 49 C.F.R. § 194.7 (2026)

(a) An operator of a pipeline for which a response plan is required under § 194.101, may not handle, store, or transport oil in that pipeline unless the operator has submitted a response plan meeting the requirements of this part. (b) An operator must operate its onshore pipeline facilities in accordance with the applicable response plan. (c) The operator of a pipeline line section described in § 194.103(c), may continue to operate the pipeline for two years after the date of submission of a response plan, pending approval or disapproval of that plan, only if the operator has submitted the certification required by § 194.119(e). [Amdt. 194-4, 70 FR 8746, Feb. 23, 2005]
Cross-references to the CFR
194.101194.103194.119