49 C.F.R. § 633.19

Exclusion from the project management oversight program.

Last amended: 2020Year: 2026Length: 99 wordsSubsections: 2Official source

Cite as 49 C.F.R. § 633.19 (2026)

The Administrator may, in compelling circumstances, determine that a project meeting the criteria of § 633.5(e)(1) is not a major capital project because project management oversight under this part will not benefit the Federal government or the recipient. Typically, this means a project that: (a) Involves a recipient whose past record indicates the appropriateness of excluding the project from project management oversight under this part; and (b) Involves such a greater level of financial risk to the recipient than to the Federal government that project management oversight under this part is made less necessary to secure the recipient's diligence.
Cross-references to the CFR
633.5
49 C.F.R. § 633.19: Exclusion from the project management oversight program. | Justis AI