49 C.F.R. § 633.23
FTA review of a project management plan.
Cite as 49 C.F.R. § 633.23 (2026)
Within 60 days of receipt of a project management plan, the Administrator will notify the recipient that:
(a) The plan is approved;
(b) The plan is disapproved, including the reasons for the disapproval;
(c) The plan will require modification, as specified, before approval; or
(d) The Administrator has not yet completed review of the plan, and state when it will be reviewed.