10 C.F.R. § 52.153

Relationship to other subparts.

Last amended: 2017Year: 2026Length: 119 wordsSubsections: 2Official source

Cite as 10 C.F.R. § 52.153 (2026)

(a) A nuclear power reactor manufactured under a manufacturing license issued under this subpart may only be transported to and installed at a site for which either a construction permit under part 50 of this chapter or a combined license under subpart C of this part has been issued. (b) Subpart B of this part governs the certification by rulemaking of the design of standard nuclear power facilities. Subpart E of this part governs the NRC staff review and approval of standard designs for a nuclear power facility. A manufacturing license applicant may reference a standard design certification or a standard design approval in its application. These subparts may also be used independently of the provisions in this subpart.
10 C.F.R. § 52.153: Relationship to other subparts. | Justis AI