20 C.F.R. § 416.574

Will you receive notice of our intention to apply cross-program recovery?

Last amended: 2016Year: 2026Length: 120 wordsSubsections: 5Official source

Cite as 20 C.F.R. § 416.574 (2026)

Before we collect an overpayment from you using cross-program recovery, we will send you a written notice that tells you the following information: (a) We have determined that you owe a specific overpayment balance that can be collected by cross-program recovery; (b) We will withhold a specific amount from the title II or title VIII benefits (see § 416.573); (c) You may ask us to review this determination that you still owe this overpayment balance; (d) You may request that we withhold a different amount from your current monthly benefits (the notice will not include this information if § 416.573(d) applies); and (e) You may ask us to waive collection of this overpayment balance. [70 FR 16, Jan. 3, 2005]
Cross-references to the CFR
416.573