23 C.F.R. § 636.513

Are limited negotiations allowed prior to contract execution?

Last amended: 2017Year: 2026Length: 114 wordsSubsections: 2Official source

Cite as 23 C.F.R. § 636.513 (2026)

(a) Yes, after the source selection but prior to contract execution, you may conduct limited negotiations with the selected design-builder to clarify any remaining issues regarding scope, schedule, financing or any other information provided by that offeror. You must comply with the provisions of § 636.507 in the exchange of this information. (b) Limited negotiations conducted under this section may include negotiations necessary to incorporate the ideas and concepts from unsuccessful offerors into the contract if a stipend is offered by the contracting agency and accepted by the unsuccessful offeror and if the requirements of section 636.113 are met. [67 FR 75926, Dec. 10, 2002, as amended at 73 FR 77502, Dec. 19, 2008]