24 C.F.R. § 884.122

Separate project requirement.

Last amended: 2016Year: 2026Length: 128 wordsSubsections: 2Official source

Cite as 24 C.F.R. § 884.122 (2026)

(a) In the case of a Private-Owner Project or a PHA-Owner Project, each Agreement and Contract shall constitute a separate project. (b) In the case of a Private-Owner/PHA Project such project may not include more than one type of Section 8 assistance, shall be processed with a separate ACC List and ACC Part I and shall be assigned a separate project number. All new construction units to be placed under a single Contract shall comprise a separate project. However, the field office director may designate as a single project the units to be covered by two or more such Contracts for new construction projects where: (1) The units are placed under ACC on the same date; and (2) Such consolidation is necessary in the interest of administrative efficiency.