Cite as 25 C.F.R. § 1000.1430 (2025)

As described in subpart I of this part, rejection of a final offer by the Secretary for a construction project must be based on a specific finding by the Secretary that clearly demonstrates, or that is supported by a controlling legal authority, that one or more of the statutory criteria under 25 U.S.C. 5366(c)(6) exist to reject the final offer.