Pub. L. 113-76, div. D, tit. III, sec. 305

Pub. L. 113-76, div. D, tit. III, sec. 305

EnactedYear: 2014Length: 61 wordsOfficial source
Sec. 305. None of the funds made available in this title may be used to approve critical decision-2 or critical decision-3 under 128 STAT. 175 Department of Energy Order 413.3B, or any successive departmental guidance, for construction projects where the total project cost exceeds $100,000,000, until a separate independent cost estimate has been developed for the project for that critical decision.
Pub. L. 113-76, div. D, tit. III, sec. 305 | Justis AI