Pub. L. 103-160, div. B, tit. XXVI, sec. 2604

LIMITATION ON TOTAL COST OF CONSTRUCTION PROJECTS.

EnactedYear: 1993Length: 74 wordsOfficial source
SEC. 2604. LIMITATION ON TOTAL COST OF CONSTRUCTION PROJECTS.Notwithstanding the cost variations authorized by section 2853 of title 10, United States Code, and any other cost variation authorized by law, the total amount of all projects carried out under section 26O1(1)(B) may not exceed the total amount authorized to be appropriated under such section and $21,400,000 (the balance of the amount authorized for the construction of a command headquarters facility at Fort McPherson, Georgia).
Pub. L. 103-160, div. B, tit. XXVI, sec. 2604: LIMITATION ON TOTAL COST OF CONSTRUCTION PROJECTS. | Justis AI