Pub. L. 100-456, div. A, tit. I, pt. B, sec. 117
MANAGEMENT OF CERTAIN DEFENSE PROCUREMENT PROGRAMS
SEC. 117. MANAGEMENT OF CERTAIN DEFENSE PROCUREMENT PROGRAMS (a) Stretchout Impact Statement.—The Secretary of Defense shall submit to Congress, at the same time the budget for any fiscal year is submitted to Congress under section 1105 of title 31, United States Code, a statement of what the effect would be during the fiscal year for which the budget is submitted of the stretchout of a major defense acquisition program if either of the following applies with respect to that program: (1) The final year of procurement scheduled for the program at the time the statement is submitted is more than two years later than the final year of procurement for the program as specified in the most recent annual Selected Acquisition Report for that program. (2) The proposed procurement quantity for that fiscal year is less than 90 percent of the procurement quantity proposed for the same fiscal year in the most recent annual Selected Acquisition Report for that program. (b) Changes in Certain Costs To Be Included.—A statement under subsection (a) with respect to a major defense acquisition program shall contain an estimate of the projected increase in unit cost and the projected increase in total program cost for the system being procured under the program compared to the program specified in the most recent annual Selected Acquisition Report for that program. (c) Identification of Stretched Out Programs.—The Secretary shall include in a statement under subsection (a) identification of all major acquisition programs for which the proposed procurement quantity for that fiscal year is less than 80 percent of the baseline production rate for that fiscal year, as defined by section 2432(c)(3)(C)(i) of title 10, United States Code, and an explanatory statement for the lower procurement rate for each program. 102 STAT. 1934 (d) Limitations.—(1) Subsection (a) shall apply only for major defense acquisition programs for which procurement is proposed at a rate of six or more units per year. (2) Subsection (a) shall not apply if the total procurement quantity has been increased, compared to the program specified in the most recent annual Selection Acquisition Report for that program, and subsection (a)(2) does not apply. (e) Report on Establishing Maximum Production Rates.—Not later than March 15, 1989, the Secretary of Defense shall submit to the Committees on Armed Services of the Senate and the House of Representatives a report on the feasibility and effect of establishing maximum production rates by December 1990 for certain major defense acquisition programs. The report shall identify and discuss ten programs, of which seven shall be programs for the procurement of conventional, tactical, or dual-capable systems. (f) Definition.—For purposes of this section, the term “major defense acquisition program” has the meaning given that term in section 2430 of title 10, United States Code.