Pub. L. 110-161, div. C, tit. I, sec. 122
Pub. L. 110-161, div. C, tit. I, sec. 122
Sec. 122. The project for flood control, Redwood River, Marshall, Minnesota, authorized by section 401(a) of the Water Resources Development Act of 1986 and modified by section 4(k) of the Water Resources Development Act of 1988 is further modified to authorize the Secretary to construct the project at a total cost of $11,863,000, with an estimated first Federal cost of $8,722,000 and an estimated first non-Federal cost of $3,141,000.