Pub. L. 110-181, div. C, tit. XXXIV, sec. 3402
REMEDIAL ACTION AT MOAB URANIUM MILLING SITE.
SEC. 3402. REMEDIAL ACTION AT MOAB URANIUM MILLING SITE. Section 3405(i) of the Strom Thurmond National Defense Authorization Act for Fiscal Year 1999 (Public Law 105–261; 10 U.S.C. 7420 note) is amended by adding at the end the following new paragraph:“(6)(A) Not later than October 1, 2019, the Secretary of Energy shall complete remediation at the Moab site and removal of the tailings to the Crescent Junction site in Utah.122 STAT. 591“(B) In the event the Secretary of Energy is unable to complete remediation at the Moab Site by October 1, 2019, the Secretary shall submit to Congress a plan setting forth the projected completion date and the estimated funding to meet the revised date. The Secretary shall submit the plan, if required, to Congress not later than October 2, 2019.”.