Pub. L. 115-244, div. A, tit. III, sec. 304 (as amended)
Pub. L. 115-244, div. A, tit. III, sec. 304 (as amended)
SEC. 304. None of the funds made available in this title may be used to approve critical decision-2 or critical decision-3 under Department of Energy Order 413.3B, or any successive departmental guidance, for construction projects where the total project cost exceeds $100,000,000, until a separate independent cost estimate has been developed for the project for that critical decision.