Pub. L. 118-159, div. B, tit. XXI, sec. 2106 (as amended)
EXTENSION OF AUTHORITY TO CARRY OUT CERTAIN FISCAL YEAR 2020 PROJECTS.
SEC. 2106. EXTENSION OF AUTHORITY TO CARRY OUT CERTAIN FISCAL YEAR 2020 PROJECTS.
(a) Extension.—Notwithstanding section 2002 of the Military Construction Authorization Act for Fiscal Year 2020 (division B of Public Law 116–92; 133 Stat. 1862), the authorizations set forth in the table in subsection (b), as provided in section 2101 of that Act (133 Stat. 1862), shall remain in effect until October 1, 2025, or the date of the enactment of an Act authorizing funds for military construction for fiscal year 2026, whichever is later.
(b) Table.—The table referred to in subsection (a) is as follows:
Army: Extension of 2020 Project Authorizations
State/Country
Installation or Location
Project
Original Authorized Amount
KwajaleinKwajalein AtollAir Traffic Control Tower and Terminal$40,000,000South CarolinaFort JacksonReception Complex, Ph2$88,000,000
- Public laws referenced
- 116-92