Pub. L. 118-47, div. A, tit. VIII, sec. 8059 (as amended)

Pub. L. 118-47, div. A, tit. VIII, sec. 8059 (as amended)

Year: 2025Length: 110 wordsOfficial source
SEC. 8059. Notwithstanding any other provision of law, funds appropriated in this Act under the heading “Research, Development, Test and Evaluation, Defense-Wide” for any new start defense innovation acceleration or rapid prototyping program demonstration project with a value of more than $5,000,000 may only be obligated 15 days after a report, including a description of the project, the planned acquisition and transition strategy and its estimated annual and total cost, has been provided in writing to the congressional defense committees: Provided,That the Secretary of Defense may waive this restriction on a case-by-case basis by certifying to the congressional defense committees that it is in the national interest to do so.
Pub. L. 118-47, div. A, tit. VIII, sec. 8059 (as amended) | Justis AI