42 U.S.C. § 16441
Funding new interconnection and transmission upgrades
Cite as 42 U.S.C. § 16441 (2026)
The Commission may approve a participant funding plan that allocates costs related to transmission upgrades or new generator interconnection, without regard to whether an applicant is a member of a Commission-approved Transmission Organization, if the plan results in rates that—
(1) are just and reasonable;
(2) are not unduly discriminatory or preferential; and
(3) are otherwise consistent with sections 824d and 824e of title 16.
(Pub. L. 109–58, title XII, § 1242, Aug. 8, 2005, 119 Stat. 962.)
- Public laws referenced
- Pub. L. 109-58