25-30.265, F.A.C.
25-30.265. Periodic Meter Tests
Cite as Fla. Admin. Code r. 25-30.265
Each utility shall inspect and test a representative sample of its meters in service at least once during the intervals set out in this rule.
Maximum Interval Size of Meter Between Tests 5/8'' 10 years 3/4'' 8 years 1'' 6 years 1 1/2'' 4 years 2'' 4 years 3'' 3 years 4'' 2 years 6'' 1 year Rulemaking Authority 350.127(2), 367.121 FS. Law Implemented 367.121(1)(a), 367.122 FS. HistoryโNew 9-12-74, Formerly 25-10.93, 25-10.093, Amended 11-10-86.