(a)
An overweight permit shall not be issued if two or
more structural members such as precast concrete
slab, prestressed concrete girders, structural steel
and other similar objects constitute the overweight.
(b) Overweight cranes, draglines, tractors and
other overweight equipment may only be moved by
disassembling them to the degree necessary for the
104-17
n 2
highway facilities to accommodate or support the loads. Such movements may require both pavement and bridge analyses. The extent of dismantling will be dependent upon the weight and size of the machine, the axle spacing and wheel arrangements of the tractor-trailer upon which the machine is transported and the theoretical load carrying capacity of bridge structures along the route of travel.
(c) Overweight mobile cranes may be required to be stripped or dismantled by removing the counter-weights, booms or outriggers as determined by structural analysis if analysis is warranted by this chapter. [Eff. MAY 30 1981 (Auth: HRS Sec. 291-36) (Imp: HRS Sec. 291-36)