HAR §19-105-5
HAR §19-105-5. Permit requirements and coordination
Cite as Haw. Code R. § 19-105-5
(a) A permit from the highways division shall be required for the installation of any utility facility and private lines within the state highway rights-of-way except where work is to be performed under a utility agreement in conjunction with a highway project.
(b) New utility installations shall not conflict with existing or planned uses of highway rights-of-way for highway purposes. Proposed utility installations and future highway projects shall be coordinated to avoid, to the fullest extent possible, any conflict in location, construction, or method of installation. [Eff. MAY 30 1981 (Auth: HRS Sec. 264-24) (Imp: HRS Sec. 264-23)]