HAR §19-127.1-21

HAR §19-127.1-21. Stockpiling of excavated material

Last amended: 1994Length: 35 wordsOfficial source

Cite as Haw. Code R. § 19-127.1-21

Excavated material should not be stockpiled, after working hours, on the roadway, shoulder, sidewalks, walkways, or ditch areas of any highway, street or road. [Eff JAN 21 1994 ] (Auth: HRS §286-8) (Imp: HRS §286-8)