HAR §19-170-196. Construction procedures

Length: 100 wordsOfficial source

Cite as Haw. Code R. § 19-170-196

(a) The subdivider shall notify the executive officer at least one week in advance of the date the subdivider will begin construction, of the contractor's name, contract price, construction schedule, and any other pertinent information, and shall file four sets of prints of the approved construction plans with each of the following: the division of engineering and division of sewers of the department of wastewater management, division of traffic planning and division of street lighting of the department of transportation services, the board of water supply, and the department of recreation; and one print with the executive officer. 170-114 306