HAR §11-280.1-70
HAR §11-280.1-70. Temporary closure
Cite as Haw. Code R. § 11-280.1-70
(a)
When an
UST system is temporarily closed, owners and operators
must continue operation and maintenance of corrosion
protection in accordance with section 11-280.1-31, and
applicable release detection in accordance with
subchapter 4. Subchapters 5 and 6 must be complied
with if a release is suspected or confirmed. Spill and
280.1-91
§11-280.1-70
overfill operation and maintenance testing and
inspections in subchapter 3 are not required during
temporary closure. If the UST system is empty, release
detection and release detection operation and
maintenance testing and inspections in subchapters 3
and 4 are not required. The UST system is empty when
all materials have been removed using commonly
employed practices so that no more than 2.5
centimeters (one inch) of residue, or 0.3 percent by
weight of the total capacity of the UST system, remain
in the system.
(b)
When an UST system is temporarily closed for
ninety days or more, owners and operators must also
comply with the following requirements:
(1)
Leave vent lines open and functioning; and
(2)
Cap and secure all other lines, pumps,
manways, and ancillary equipment.
(c)
When an UST system is temporarily closed for
more than twelve months, owners and operators must
permanently close the UST system if it does not meet
the applicable design, construction, and installation
requirements in subchapter 2, except that the spill
and overfill equipment requirements do not have to be
met. Owners and operators must permanently close the
substandard UST systems at the end of this twelve
month period in accordance with sections 11-280.1-71
to 11-280.1-74, unless the department provides an
extension of the twelve-month temporary closure
period. Owners and operators must complete a site
assessment in accordance with section 11-280.1-72
before such an extension can be applied for.
[Eff
7/15./18;20c.omp 1/17/20; comp 7/8/21; comp
MAH 21
Z:J
)
(Auth:
HRS §§342L-3, 342L-37)
(Imp:
HRS §§342L-3, 3421-37)
§11-280.1-71
Permanent closure and changes-in
service.
(a)
At least thirty days before beginning
either permanent closure or a change-in-service of an
UST or tank system under subsections (c) and (d),
owners and operators must notify the department of
280.1-92
3 5 8 4 ..
§11-280.1-71
their intent to permanently close or make the change
in-service, as required in section 11-280.1-34, unless
such action is in response to a confirmed release. The
required assessment of the excavation zone under
section 11-280.1-72 must be performed after notifying
the department but before completion of the permanent
closure or change-in-service.
(b)
At least seven days before excavation work
for a permanent closure or change-in-service, owners
or operators must notify the department of the exact
date that the work will occur, as required in section
11-280.1-34.
(c)
To permanently close an UST or tank system,
owners and operators must:
(1)
Empty and clean the UST and tank system by
removing all liquids and accumulated
sludges;
(2)
Remove the UST or tank system from the
ground, fill the UST or tank system with an
inert solid material, or close the tank in
place in a manner approved by the
department; and
(3)
Conduct a site assessment in accordance with
section 11-280.1-72.
(d)
Continued use of an UST system to store a
non-regulated substance is considered a change-in
service. Before a change-in-service, owners and
operators
( 1)
( 2)
must:
Empty and clean the UST and tank system by
removing all liquids and accumulated
sludges; and
Conduct a site assessment in accordance with
section 11-280.1-72.
(e)
Within thirty days of completing a permanent
closure or change-in-service, owners and operators
must submit to the department:
(1)
A notification as required in section
11-280.1-34; and
(2)
A UST closure report, including the results
of the site assessment conducted in
accordance with section 11-280.1-72.
[Eff
7/15/18; comp 1/17/20; am and comp 7/8/21;
280.1-93
3 5 8 4
..
§11-280.1-72
comp MAR 2 1 202è
342L-37)
(Imp:
]
(Auth:
HRS §§342L-3,
HRS §§342L-3, 342L-37)
§11-280.1-72
Assessing the site at closure or
change-in-service.
(a)
Before permanent closure or a
change-in-service is completed, owners and operators
must measure for the presence of a release where
contamination is most likely to be present at the UST
site. In selecting sample types, sample locations, and
measurement methods, owners and operators must
consider the method of closure, the nature of the
stored substance, the types of backfill and
surrounding soil, the depth and flow of groundwater,
and other factors appropriate for identifying the
presence of a release. The requirements of this
section are satisfied if one of the external release
detection methods allowed in section 11-280.1-43(5)
and (6) is operating in accordance with the
requirements in section 11-280.1-43 at the time of
closure, and indicates no release has occurred.
(b) If contaminated soils, contaminated
groundwater, or free product as a liquid or vapor is
discovered under subsection (a), or by any other
manner, owners and operators must begin release
response action in accordance with subchapter 6.
JEff
7/15/18; comp 1/17/20; comp 7/8/21; comp MAR 212025
]
(Auth:
HRS §§3421-3, 342L-37)
(Imp:
HRS §§342L-3, 342L-372)
§11-280.1-73
Applicability to previously closed
UST systems.
(a)
When directed by the department,
the owner and operator of an UST system permanently
closed before December 22, 1988 must assess the
excavation zone and close the UST system in accordance
with this subchapter if releases from the UST may, in
the judgment of the department, pose a current or
potential threat to human health and the environment.
(b)
When directed by the department, the owner
280.1-94
3 5 8 4
.,
§11-280.1-75
and operator of an UST system with field-constructed
tanks or an airport hydrant fuel distribution system
permanently closed before August 9, 2013 must assess
the excavation zone and close the UST system in
accordance with this subchapter if releases from the
UST may, in the judgment of the department, pose a
current or potential threat to human health and the
environment.
[Eff 7/15/18; comp 1/17/20; comp 7/8/21;
comp MAR 21 2025
1
(Auth: HRS
§§342L-3, 3421-37)
(Imp:
HRS §§3421-3, 342L-37)