HAR §6-17-9
HAR §6-17-9. Fee agreement
Length: 350 wordsOfficial source
Cite as Haw. Code R. § 6-17-9
An executed copy of a fee agreement in the
form prescribed by the director shall be submitted with the application. The fee
agreement shall obligate the project party to reimburse the department and the
State for any and all costs and expenses incurred in:
(1)
The processing and reviewing of the project party's application for
assistance under part VIII, chapter 39A, HRS, whether or not the
special purpose revenues bonds are ultimately issued to finance the
project; and
(2)
The issuance of bonds to finance a loan to the project party.
[Eff
APR 1 1 20l1S
] (Auth: HRS §26-38) (Imp: HRS
§39A-254)
§§6-17-10 to 6-17-12 (Reserved)
SUBCHAPTER 3
REV lEW PROCbSS
~6-17-13 Determination of re~J29!1Sibility. The department shall
determine whether a project party is a responsible party. The determination shall
be made on a case-by-case basis. The following elements shall be considered in
making the determination:
17-4
§6-17-15
(1)
The experience of the project party in providing elementary,
secondary, and post-secondary education to the general public
and in providing the type of service represented by the project;
(2)
The financial condition of the project party and the ability of the
project party to make the payments that would be required by the
project agreement from reveuut:s ueiivt:u frum tht: prujet:t or
otherwise;
(3)
The security proposed for the loan including, if any, the real or
personal property, or both, to be pledged, mortgaged, or leased,
and the presence of a guaranty of a third party, including a
controlling party of the project party;
(4)
If determined necessary or desirable by the department, a
financial feasibility study prepared by an independent party
approved by the department, or other projection of the future
ability of the project party to repay the loan;
(5)
The project party's credit reputation including, if the project has
been previously financed, the project party's experience with
respect to the prior financing of the project; and
(6)
Any other factors the department deems relevant to a
determination of responsibility with respect to any project party.
[Eff
APR 1 1 Lffl>
] (Auth: HRS §26-38) (Imp: HRS
§39A-254)