HAR §13-169-53
HAR §13-169-53. Term of permit
Cite as Haw. Code R. § 13-169-53
(a) Every permit
approved and issued by the commission shall be for a
specified period, not to exceed two years, unless
otherwise specified in the permit.
(b)Every permit approved and issued by the
commission shall contain the commencement and
completion dates for the permitted activity. In
determining the commencement and completion dates of
the activity, the commission shall take into
consideration the:
(1)
Cost and magnitude of the project;
(2)
Engineering and physical features involved;
(3)
Existing conditions; and
(4)
Public interests affected.
(c)
The commission may extend the completion
dates of the activity prescribed in any permit upon a
showing of good cause and good-faith performance.
(d)
If the commencement or completion date is
not complied with, the department shall notify the
permittee by certified mail that the permit shall be
revoked within sixty days unless the permittee can
show good cause that it should not be revoked. [Eff.
MAY 27 1988] (Auth: HRS §174C-8) (Imp: HRS
§§174C-5, 174C-71)