HAR §13-183-56
HAR §13-183-56. Amendments to plan operations
Cite as Haw. Code R. § 13-183-56
After completion
of all operations authorized under any previously approved plan
of operation, the lessee shall not begin to redrill, repair,
deepen, plug back, shoot, or plug and abandon any well, make
casing tests, alter the casing or liner, stimulate production,
change the method of recovering production, or use any formation
or well for brine or fluid injection until the chairperson has
31
received and approved in writing a new or amended plan of
operation. In an emergency a lessee may take action to prevent
damage without receiving prior approval from the chairperson;
provided, that the lessee shall report the action to the
chairperson as soon as possible. [Eff. JUN 22 1981] (Auth:
HRS §182-14) (Imp: HRS §§182-7, 182-14)