HAR §13-183-74
HAR §13-183-74. Blowout-prevention equipment
Cite as Haw. Code R. § 13-183-74
(a) Blowout-
prevention equipment ("BOPE") capable of shutting-in the well
during any operation shall be installed on the surface casing
tested and shall be maintained ready for use at all times. BOPE
pressure tests may be observed by the chairperson or his
designated representative on all exploratory wells prior to
drilling out the shoe of the surface casing. The decision to
require and observe BOPE pressure tests on other types of wells
shall be made on a well-to-well basis. The chairperson shall be
contacted in advance of a scheduled pressure test to allow time
for travel to the well site to witness the test.
BOPE installations shall include high temperature-rated
packing units and ram rubbers if available and shall have a
minimum working-pressure rating equal to or greater than the
lesser of:
(1)
A pressure equal to the product of the depth of the
BOPE anchor string in feet times one psi per foot;
(2)
A pressure equal to the rated burst pressure of the
BOPE anchor string; or
(3)
A pressure equal to 2,000 psi.
(b)
The requirements for blowout-prevention equipment shall
be subject to review and modification by the chairperson. The
following standards serve as guidelines for preparation of
minimum blowout-prevention programs:
(1)
No BOPE is required for known shallow, low temperature,
low pressure areas where down-hole water temperatures
are less than one hundred degrees Celsius at depths
less that five hundred feet or where temperatures and
pressures are unknown and the proposed depth of drillis
less than five hundred feet.
(2)
CLASS 2M BOPE (API CLASS 2M-A or 2M-RE) is required for
low pressure areas where known temperatures are above
one hundred degrees Celsius at depths less than 2,000
feet, or where sub-surface temperatures and pressures
are unknown and the proposed depth of drilling is less
than 2,000 feet. Equipment shall include:
(A)
An annular BOPE or pipe-ram/blind-ram BOPE with
minimum working-pressure ratings of 1,000 psi
installed on the surface casing so that the well
can be shut-in at any time;
41
(B)
Hydraulic and/or manual actuating system;
(C)
Kelly cock;
(D)
A fill-up line installed above the BOPE;
(E)
A kill line installed below the BOPE, leading
directly to the mud pumps and fitted with a valve
through which cement could be pumped if necessary;
and
(F)
A blow-down line fitted with two valves installed
below the BOPE. The blow-down line shall be
directed in a manner so as to permit containment
of produced fluids and to minimize any safety
hazard to personnel.
(3)
CLASS 3M BOPE (API CLASS 2M-RSRA or EQUIVALENT) is
required for medium pressure areas where subsurface
pressures are less than 1000 psi or where pressures are
unknown and the proposed total depth of the well is
greater than 2000 feet. Equipment shall include:
(A)
Annular BOPE and pipe-ram/blind-ram BOPE with a
minimum working-pressure rating of 2,000 psi
installed on the surface casing so that the well
can be shut-in at any time and with a double-ram
preventer having a mechanical locking device;
(B)
A hydraulic actuating system utilizing an
accumulator of sufficient capacity and a high
pressure auxiliary backup system equipped with
dual controls, one at the driller's station and
one at least fifty feet away from the well head;
(C)
Kelly cock and standpipe valve;
(D)
A fill-up line installed above the BOPE;
(E)
A kill line installed below the BOPE, leading
directly to the mud pumps and fitted with a valve
through which cement could be pumped if necessary;
and
(F)
A blow-down line fitted with two valves installed
below the BOPE with blow-down line directed in
such a manner as to permit containment of produced
fluids and to minimize any safety hazard to
personnel.
(4)
CLASS 1A BOPE is required in areas where dry steam is
known to exist and/or formation pressures are less than
hydrostatic and air is used as the drilling medium.
Equipment shall include:
(A)
A rotating-head installed at the top of the BOPE
stack;
(B)
A pipe-ram/blind-ram BOPE, with a minimum working-
pressure rating of 1,000 psi, installed below the
rotating-head so that the well can be shut-in at
any time;
42
(C)
A banjo-box steam diversion unit installed below
the double-ram BOPE, fitted with a muffler capable
of lowering sound emissions to within acceptable
standards;
(D)
A blind-ram BOPE, with a minimum working-pressure
rating of 1,000 psi, installedbelow the banjo-box
so that the well can be shut-in while removing the
rotating-head during bit changes;
(E)
A gate valve required on final casing string to be
cemented back to surface, with a minimum working-
pressure rating of three hundred psi, installed
below the blind-ram so that the well can be shut-
in after the well has been completed, prior to
removal of the BOPE stack;
(F)
All ram-type BOPE shall have a hydraulic actuating
system utilizing an accumulator of sufficient
capacity and a high-pressure backup system, one at
the driller's station and the other at least fifty
feet away from the well head;
(G)
Kelly cock and standpipe valves;
(H)
A kill line installed below the BOPE, leading
directly to the mud pumps and fitted with a valve
through which cement could be pumped if necessary;
and
(I)
A blow-down line fitted with two valves installed
below the BOPE. This line shall be directed so as
to minimize any safety hazard to personnel. If
any portion of a well is drilled using mud, Class
2M BOPE shall be installed on the surface casing
so that the well can be shut-in at any time.
[Eff. JUN 22 1981] (Auth: HRS §182-14)
(Imp: HRS §182-
14)