HAR §13-183-76
HAR §13-183-76. Well tests
Cite as Haw. Code R. § 13-183-76
(a) The chairperson shall require
the well tests or remedial work as necessary to prevent and
43
minimize damage to life, health, property, natural resources,
geothermal resources, ground water resources, and the
environment. Tests may include casing tests, cementing tests,
directional tests, or equipment tests.
(b)
All casing strings shall be pressure tested after
cementing and before commencing any other operations on the well.
Minimum casing test pressure shall be approximately one-third of
the manufacturer's rated internal yield pressure; provided that
the test pressure shall not be less than six hundred pounds per
square inch and greater than 1500 pounds per square inch. In
cases where combination strings are involved, the above test
pressures shall apply to the lowest pressure-rated casing used.
Test pressures shall be applied for a period of thirty minutes.
If a drop of more than ten percent of the test pressure should
occur, the casing or cement job shall be considered defective and
corrective measures shall be taken before commencing any further
operations on the well.
(c)
If the cementing of any casing appears to be defective,
or if the casing in any well appears to be defective or corroded
or parted, or if there appears to be any underground leakage for
whatever other reason which may cause or permit underground
waste, the operator shall proceed with diligence to use the
appropriate method or methods to eliminate the hazard. If the
hazard of waste cannot be eliminated, the well shall be plugged
and abandoned in accordance with a plugging program approved by
the chairperson.
(d)
All wells shall be tested to determine the deviation
from the vertical at maximum intervals of five hundred feet or
less. [Eff. JUN 22 1981] (Auth: HRS §182-14) (Imp: HRS
§182-14)
Subchapter 9. Drilling; Modification of Well for Injection Use