HAR §15-109-5
HAR §15-109-5. Development permit required
Cite as Haw. Code R. § 15-109-5
(a) No development within the
convention center district shall be initiated, and no building permit shall be issued for the
development, unless the developer has obtained from the authority a development permit
certifying that the development complies with the provisions and requirements of the
convention center development plan and this chapter.
(b) An application to the authority for a development permit shall include complete
and detailed information showing that the development complies with the provisions and
requirements of the convention center development plan and this chapter. The authority
may determine the nature and extent of the information required in the application.
(c) The authority may include in any development permit such conditions
concerning the development or the development permit, or both, which the authority
deems necessary or appropriate to implement the purposes, policies, and provisions of the
convention center development plan and this chapter.
(d) The authority shall take final action upon an application for a development
permit in a reasonably prompt manner, and shall give the applicant adequate notice of its
final action immediately upon taking final action.
(e) This section shall not apply to:
(1) Development by the developer whose convention center development plan has
been given final approval by the authority pursuant to chapter 15-107,, which
is pursuant to the convention center development plan, which shall be
governed by the development agreement between the authority and the
developer;
(2) Development initiated by the authority; and
(3) Any project or activity of any county or agency of the State within the
convention center district, which shall be constructed, renovated, or improved
in consultation with the authority. [Eff 11/20/89; am and comp FEB 25 1994]
(Auth: HRS §§206X-4, 206X-6) (Imp: HRS §§206X-4, 206X-6, 206X- 9)