HAR §15-15-79
HAR §15-15-79. Performance time
Length: 208 wordsOfficial source
Cite as Haw. Code R. § 15-15-79
(a)
Petitioners
granted district boundary amendments shall make
15-78
§15-15-80
substantial progress within a reasonable period, as
specified by the commission, from the date of approval
of the boundary amendment, in developing the property
receiving the boundary amendment. The commission may
act to amend, nullify, change, or reverse its decision
and order if the petitioner fails to perform as
represented to the commission within the specified
period.
(b)
The commission may provide by condition that
absent substantial commencement of use of the subject
property or substantial progress in developing the
land receiving the boundary amendment in accordance
with representations and commitments made by the
petitioner to the commission, the commission shall
issue and serve upon the party bound by the condition
an order to show cause why the property should not
revert to· its former land use district classification
or be changed to a more ~ppropriate land use district
classification.
Such conditions, if any, shall run
with the land and be recorded in the bureau of
conveyances pursuant to section 15-15-92.
[Eff
10/27/86; am and comp all6/97; comp 5/8/00; am and
comp 11/2/2013; comp
UI; I 1 8 2019
J (Auth:
HRS
§§205-1, 205-4, 205-7)
(Imp:
HRS §205-4)
SUBCHAPTER 9
POST HEARING PROCEDURES FOR HEARINGS BEFORE
THE COMMISSION·