HAR §15-215-75

HAR §15-215-75. Temporary use permit

Length: 142 wordsOfficial source

Cite as Haw. Code R. § 15-215-75

(a) Applicability. Structures, such as tents and booths, may be permitted by the executive director for periods not exceeding fourteen consecutive days within a ninety-day period, provided that for good reasons, the executive director may grant extensions. (b) Initiation. An applicant may apply for a temporary use permit by filing an application with the executive director and payment of the requisite fee listed in section 15-215-91. (c) Action. In accordance with Figure 1 (approval requirements matrix), dated November 2025, made a part of this chapter, and attached at the end of this chapter, the executive director may approve all temporary use permit applications consistent with this section. In approving a temporary use permit, the 215-86 executive director may impose reasonable standards, conditions, or requirements as a condition of approval. [Eff ] (Auth: HRS §§206E-4, 206E-5, 206E-7) (Imp: HRS §§206E-4, 206E-5, 206E-7) [§15-215-77]