(a) The following permits shall be deemed approved and require no public hearing if a certificate of completeness has been issued and no decision is rendered within the following review periods: (1) Rules clearance (sixty calendar days); (2) Facility Permit (ninety calendar days); and (3) Variance (one hundred eighty calendar days). (b) Whenever a proposed project requires more than one permit, the longest review period of this section shall apply for determining the deemed approved date. [Eff AUG 0 9 2021] (Auth: HRS §§206E-4, 206E-5, 206E-7) (Imp: HRS §§206E-4, 206E-5, 206E-7)