HAR §15-22-23
HAR §15-22-23. Automatic approvals
Cite as Haw. Code R. § 15-22-23
(a) The following
development-related permits and approvals shall be deemed
approved if no decisions are made granting or denying them
within the following review periods:
UNOFFICIAL COMPILATION
June 2005
22-23
(1) Master plan permits: 200 days;
(2) Planned development permits: 160 days;
(3) Base zone development permits: 160 days;
(4) Certificates of appropriateness: 160 days;
(5) Conditional use permits for off-site parking or
joint use of parking: 160 days;
(6) Variances: 100 days;
(7) Modifications: 100 days;
(8) Certificates of project eligibility: 60 days;
(9) Conditional use permits for vacant land: 30 days;
(10) Zoning adjustments and waivers: 30 days; and
(11) Temporary use permits: 10 days.
(b) The review period shall commence upon submission
of a complete application. In the event that no decision is
rendered on the application within ten (10) days of the
submission of a complete application, the applicant shall be
notified of the date for automatic approval.
(c) When a proposed project requires more than one
permit and/or approval listed in subsection (a) of this
section, the applicant may apply for some or all such
approvals concurrently. The review period for concurrent
applications shall be based on the permit or approval with
the longest review period.
(d) Application filing procedures and preparation
guidelines
may
be
provided
to
assist
applicants.
[Eff 1/13/00] (Auth: HRS §§206E-4, 206E-5, 206E-7) (Imp:
HRS §§206E-4, 206E-5, 206E-7)
§15-22-24 to §15-22-29 (Reserved)