HAR §15-23-10
HAR §15-23-10. Project eligibility review
Cite as Haw. Code R. § 15-23-10
(a) The
executive director may require, prior to receipt of
any application for a development permit, a project
eligibility review of the development project to
consider the project's relationship to the makai area
plan, its impact on infrastructure facilities such as
streets, pedestrian and bicycle circulation, sanitary
sewers, drainage and water, and to improve efficiency
and avoid unnecessary delays and expense in processing
the formal development application. No development
application for which a project eligibility review has
§15-23-11
23-17
been required shall be considered until the project
eligibility review has been completed.
(b) To conduct project eligibility review, the
applicant shall provide sufficient information that
the executive director may reasonably request, such as
the proposed site plan, basic massing, floor area
allocation and location of proposed uses, off-street
parking and loading, pedestrian and vehicular
circulation, topography (existing and proposed), and
location of existing and proposed improvements and
utilities.
(c) To the extent possible, project eligibility
review shall be completed within thirty days of the
executive director's determination to require the
review.
(d) Developments shall not be approved unless
adequate infrastructure facilities are or will be made
available to service the proposed development prior to
occupancy. The executive director may consult with
applicable governmental agencies regarding the
adequacy of infrastructure requirements. Any
development approval may be conditioned with the
requirement that the concerns and requirements of
appropriate governmental agencies relative to the
adequacy of infrastructure facilities for the proposed
development are satisfied.
(e) Notwithstanding the requirement for a
project eligibility review, potential applicants may
seek preliminary review of their proposed developments
with the executive director prior to submitting an
application for a development permit. [Eff 2/24/90;
am and comp 10/10/98; comp 2/2/02; comp 12/9/02; comp
11/3/05] (Auth: HRS §§206E-4, 206E-5, 206E-7)
(Imp: HRS §§206E-4, 206E-5, 206E-7)