HAR §15-23-16
HAR §15-23-16. Application fees
Cite as Haw. Code R. § 15-23-16
(a) The following fee schedule shall be applicable to all permits, rule clearance, and public hearings.
Permit Fee Schedule (12/1/23)
| Rule | Permit | Fee Amount |
| --- | --- | --- |
| §15-23-14.1 | Variance | $500 plus the cost of public hearing |
| §15-23-24 | Zoning Clearance | $50 |
| §15-23-25 | Rules Clearance | $50 |
| §15-23-26 | Renovation Permit | $50 |
| §15-23-27 | Improvement Permit | Project size up to 1,000 square feet (sf): $50 |
| | | Project size of 1,001 sf to 10,000 sf: $100 |
| | | Project size of 10,001 sf to 20,000 sf: $500 |
| §15-23-27 | Development Permit | $6,400 plus the cost of public hearing |
| §15-23-78 | Temporary Use Permit | $50 |
| §15-23-79 | Conditional Use of Vacant Land | $50 |
15-23-28
1352
§15-23-19
| Rule | Permit | Fee Amount |
| --- | --- | --- |
| §15-23-82.1 | Conditional Use Permit | $500 plus the cost of public hearing |
| §15-23-178 | Master Plan Permit | $10,000 plus the cost of public hearing |
(b) Government agencies shall be exempt from all fees required by this chapter. [Eff 2/24/90; am and comp 10/10/98; comp 2/2/02; comp 12/9/02; comp 11/3/05; am and comp ] (Auth: HRS §§206E-4, 206E-5) (Imp: HRS §§206E-4, 206E-5)