HAR §15-23-26
HAR §15-23-26. (c) Action
Cite as Haw. Code R. § 15-23-26
In accordance with Figure 2 (approval requirements matrix), dated November 2023, made a part of this chapter, and attached at the end of this chapter, the executive director shall approve all rules clearance applications consistent with this section after receipt of a complete application and payment of the requisite fee.
(d) Exceptions. Building permits can be approved without an associated rules clearance permit in the following cases:
(1) Standalone interior electrical or plumbing work that would otherwise comply with section 15-23-25(a);
(2) Changes in use that are still permitted under subchapter 2. [Eff JAN 18 2024] (Auth: HRS §§206E-4, 206E-5, 206E-7) (Imp: HRS §§206E-4, 206E-5, 206E-7)
###