HAR §15-36-07. Permit plan application contents
Length: 387 wordsOfficial source
Cite as Haw. Code R. § 15-36-07
The
permit plan application shall include:
(1)
The legal name of the applicant and location
of the principal place of business, and if
the applicant is a corporation, limited
liability company, trust, or other
organization, the state in which the
applicant was organized or incorporated.
(2)
The name, title, and address of the person
to whom correspondence or communications in
regard to the application are to be
addressed.
(3)
Description of the subject property ~pon
which the proposed renewable energy facility
will be developed, including tax map key
number and location maps.
(4)
Description of:
(A)
The renewable energy facility,
including the identification of the
category of renewable energy as defined
in section 269-91, HRS;
(B)
Any renewable energy production
structure or equipment;
(C)
Any energy transmission line for the
facility to a public utility's
electricity transmission or
distribution system;
(D)
Any on-site and off-site
infrastructure, and any on-site
building, structure, other improvement,
or equipment necessary for the
production of electricity or biofuel
from the renewable energy site,
36-6
§15-36-07
transmissio~ of the electricity or
biofuel, or any accommodation for
employees of the facility.
(5)
Description of all federal, state, and
county permits reasonably anticipated by the
applicant to be necessary for approval of
the renewable energy facility, including a
proposed plan for all permits to be
processed concurrently, along with a
proposed plan to coordinate the issuance of
delegated environmental permits, a proposed
timeline for coordination of permit
processing with potential environmental
impact statements, and an anticipated list
of required federal, state, and county
technical support and data required.
(6)
A true copy of all pending applications for
federal, state, and county permits
previously submitted and reasonably
anticipated by the applicant to be necessary
for approval of the renewable energy
facility.
These are permits applied for
prior to applying for a renewable energy
facility permit plan.
(7)
A true copy of all completed applications
for all other federal, state, and county
permits previously submitted and reasonably
anticipated by the applicant to be necessary
for approval of the renewable energy
facility.
These are permits that have
already been granted to the proj'ect prior to
applying for a renewable energy facility
permit plan.
(8)
Any other information deemed necessary by
the energy resources coordinator or
renewable energy facilitator.
[Eff.
JUL() 12010
l
(Auth: HRS §201N-12) (Imp:
HRS
§201N-3)