HAR §16-131-59
HAR §16-131-59. Repairs and maintenance
Cite as Haw. Code R. § 16-131-59
(a) The cable operator shall
schedule or acknowledge subscriber requests for repair or maintenance service
within twenty-four hours (excluding weekends and holidays).
(b)
The cable operator shall verify and complete the repair or
maintenance service within forty-eight hours (excluding weekends and holidays)
after a subscriber request for repair or maintenance has been acknowledged or
scheduled.
(c)
If the cable operator anticipates taking longer than forty-eight hours
to complete the repair or maintenance service due to a system problem, the cable
operator shall submit a written notice to the director stating the circumstance of the
problem and when the cable operator expects the service in subsection (b) will be
restored. [Eff and comp 12/23/91; comp 12/3/08] (Auth: HRS §440G-12) (Imp:
HRS §440G-12)