HAR §11-20-30. that the new or modified public water system will deliver water in compliance with state primary drinking water regulations before construction

Length: 784 wordsOfficial source

Cite as Haw. Code R. § 11-20-30

A proposed or existing supplier of water or its duly authorized representative shall provide the following information: (1) Plans, specifications, supporting information, and documents detailing the design and location of the proposed new public water system or the existing public water system and the proposed substantial modifications; (2) Documents and supporting information on the raw water source(s) and proposed treatment, if any, demonstrating that the source(s) of raw water to supply the public water system complies with state primary drinking water regulations. Where a new source of raw water is proposed to supply a public water system, the documents must demonstrate that the new source of raw water complies with section 11-20-29; (3) Documents and information demonstrating that the public water system will be adequately operated and maintained; (4) Documents and information demonstrating that the new public water system or substantial modifications to an existing public water system will be located and constructed in conformance with all applicable State of Hawaii laws and county ordinances relating to floods, tsunamis, earthquakes, and fires. To the extent practicable, part or all of the new or substantially modified existing facility shall avoid any site which is subject to a significant risk from earthquakes, floods, tsunamis, fires, or other disasters which could cause a breakdown of the public water system or a portion thereof or which is, except for intake structures, within the floodplain of a hundred-year flood or is lower than any 20-150 3376 1 §11-20-30 recorded high tide where appropriate records exist; (5) Certification by the licensed professional engineer(s) responsible for the preparation of the plans and specifications for the new public water system or the substantial modifications to the existing public water system, and the operation and maintenance documents, that the water system or the modifications have been designed to deliver water that will comply with state primary drinking water regulations. This certification is not required for plans and specifications prepared by personnel in the county department or board of water or water supply, in compliance with applicable county department or board of water or water supply rules, regulations, and standards; (6) Certification by the proposed or existing supplier of water that the public water system will be operated and maintained to provide water in compliance with state primary drinking water regulations. This certification is not required for new or modified public water systems owned and operated by the county department or board of water or water supply; and (7) Other information, including testing or inspections, as the director considers necessary to decide on whether to grant approval to construct. (c) After construction has been completed, the new public water system or substantial modifications to an existing public water system shall not be used to deliver water to any user until approved by the director. The supplier of water or its duly authorized representative shall provide the following: (1) A detailed description of the changes made from the planned system or modification approved by the director and analysis of the effect, if any, that the changes will have on the quality of water delivered by the new 20-151 3376 H §11-20-30 or modified public water system and compliance with primary drinking water regulations, certified by a licensed professional engineer; and (2) Other information, including testing or inspections, as the director considers necessary to approve of the changes or evaluate the need for corrective actions. (d) For approval of a new community public water system or a new non-transient non-community public water system, required under subsection (a), before construction or use of the system, the proposed supplier of water or its duly authorized representative shall comply with the requirements of subsection (b) and demonstrate to the director's satisfaction that the proposed system has adequate capacity as described in section 11-20-29.5. (1) A new community public water system or new non-transient non-community public water system shall include: (A) Newly constructed community public water systems or non-transient non-community public water systems; and (B) Water systems that do not currently meet the definition of a public water system as defined in section 11-20-2 but which expand their infrastructure and thereby grow to become a community public water system or a non-transient non-community public water system; and (2) A demonstration of adequate capacity under section 11-20-29.5 shall include the obtaining of the director's approval of any new sources of raw water as described in section 11-20-29. (e) For approval of a new transient non-community public water system or substantial modification of an existing public water system, which has failed to comply with state primary drinking water regulations or has significant problems noted by sanitary surveys or inspections, required under subsection (a), the proposed or existing supplier of 20-152 3376 [Unreadable]
HAR §11-20-30: HAR §11-20-30. that the new or modified public water system will deliver water in compliance with state primary drinking water regulations before construction | Justis AI