85-020
Authority of Capital Development Board to Determine Whether a Community College Building Was Defectively Designed or Constructed
Cite as Ill. Op. Att'y Gen. No. 85-020
SEAL vas THE STATE ILLINOIS
AUG.
2611
NEIL F. HARTIGAN
ATTORNEY GENERAL
STATE OF ILLINOIS
SPRINGFIELD
November 19, 1985
FILE NO. 85-020
ADMINISTRATIVE LAW:
Authority of Capital Development
Board to Determine Whether a
Community College Building Was
Defectively Designed or Constructed
Gary J. Skoien, Executive Director
Capital Development Board
3rd Floor/William G. Stratton Building
401 South Spring Street
Springfield, Illinois 62706
Dear Mr. Skoien:
I have your letter wherein you pose the following
questions:
1. May the Capital Development Board [CDB], under
section 5-12 of the Public Community College Act
(Ill. Rev. Stat. 1983, ch. 122, par. 105-12),
determine whether building defects in a community
college building are the result of design error
or defective construction when the parties have
settled the claim or claims arising from the
building defects thereby precluding a judicial
determination on causation or fault?
Gary J. Skoien - 2.
2. Does a release executed by the college in
question and the Illinois Building Authority
[IBA] in the course of settling the claim or
claims emanating from building defects in a
college building, as hereinafter described,
preclude the CDB from using State funds, pursuant
to section 5-12 of the Public Community College
Act, to correct the building defects?
You have advised this office of the factual background
which has precipitated your questions. In January, 1968, the
IBA entered into an agreement with a general contractor for the
construction of a building at Sauk Valley College. A certifi-
cate of substantial completion was issued to the contractor in
November, 1969, but prior to the actual completion of the
construction project, Sauk Valley College, hereinafter referred
to as the College, observed cracking and spalling in the cast-
in-place exterior concrete and in four concrete load-bearing
columns. Secondary to these problems, water penetration of the
walls and other interior damage occurred. It appears that, at
that juncture, the contractor had not been paid in full. In
1972, the contractor brought suit against the IBA, the College
and the architect/engineer [A/E] of the project for damages
resulting from the delay in payment. The contractor alleged
that the plans and specifications given to it were incomplete
and inaccurate, that performance of certain contractual obli-
gations was impossible, and that the A/E failed to carry out
its duties under its contract with the IBA properly. In turn,
Gary J. Skoien - 3.
the IBA and the College counterclaimed against the contractor
for defective work.
In 1977, however, the parties settled the lawsuit on
the following terms:
A. The contractor released the IBA, the College, and
the A/E from all claims arising out of the construction of the building.
B. The A/E agreed to pay the contractor $100,000.
C. The IBA released the contractor and the A/E from
all claims arising out of design and construction
of the College building.
D. The College released any claims it had against
the contractor and the A/E and agreed to assume
$100,000 of repair costs. Since at the time of
the settlement the repair costs were estimated at
$200,000, the IBA agreed to seek the additional
$100,000 from the CDE and the General Assembly.
E. The A/E released the IBA, the College, and the
contractor from all claims.
Subsequent to the above-described settlement, the
College was advised that the repair costs would be much higher
than the original estimate of $200,000, and as a consequence
thereof, the College has requested the CDB to provide State
funding to correct the building defects pursuant to section
5-12 of the Public Community College Act. You have not
indicated that the College and the IBA did not use due
diligence to ascertain the true amount of damages or that they
did not reasonably and in good faith enter into the settlement.
Section 5-12 of the Public Community College Act (Ill.
Rev. Stat. 1983, ch. 122, par. 105-12), provides as follows:
Gary J. Skoien - 4.
"In the event the Capital Development Board
determines that a facility previously provided
for a community college under this Article was
defectively designed or constructed, the cost of
any necessary corrective work shall be fully
funded by monies appropriated pursuant to the
Capital Development Bond Act of 1972, as now or
hereafter amended. In such an instance, the
community college shall not be required to provide any portion of the cost of the corrective
work.
Should a community college district recover
damages against any party responsible for the
defective design or construction of a community
college facility, the community college district
shall reimburse the State of Illinois for any
funds provided by the State to correct building
defects.
No provision of this Section shall preclude
or delay litigation by a community college district to recover damages for such defective
design or construction from the party or parties
responsible for same."
In construing a statute, the intent of the General Assembly
should be ascertained and given effect. (City of Springfield
V. Board of Election Commissioners of the City of Springfield
(1985) 105 Ill. 2d 336, 340-41; Illinois National Bank V.
Chegin (1966), 35 Ill. 2d 375, 378.) Legislative intent is
ascertained primarily from a consideration of the statute's
language. (Droste V. Kerner (1966), 34 Ill. 2d 495, 503, cert.
denied, 385 U.S. 456, 87 S. Ct. 612 (1967); People V. Crete
(1985), 133 Ill. App. 3d 24, 32.) If the legislative intent
can be ascertained from the language of the statute, it must
prevail and be given effect. General Motors Corp. V. Indus-
trial Commission (1975), 62 Ill. 2d 106, 112.
Gary J. Skoien - 5.
Moreover, it is fundamental that an agency of govern-
ment possesses only those powers conferred by express provision
of the law or those powers which are incident to express powers
conferred for the purpose of effectively accomplishing the
objectives for which the agency was created. Aurora East
Public School District No. 131 V. Cronin (1982), 92 Ill. 2d
313, 326; City of Waukegan V. Pollution Control Board (1974),
57 Ill. 2d 170, 184; City of Chicago V. State and Municipal
Teamsters (1984), 127 Ill. App. 3d 328, 336.
Pursuant to section 5-12 of the Public Community
College Act, the General Assembly has expressly delegated to
the CDB the power to determine whether a community college
facility was defectively designed or constructed. Furthermore,
the General Assembly has provided that, in the event that a
community college recovers damages from a responsible party,
the CDB must be reimbursed for the funds provided by the
State. On the basis of these provisions, it is clear that the
General Assembly intended that the CDE independently exercise
its power to make determinations regarding defective design and
construction and that the exercise of such power is not contin-
gent upon any judicial findings or rulings on the issue. While
the resolution of the issues of defective design and construction may involve complicated questions of fact, it is clear
that a governmental agency has the authority to decide such
Gary J. Skoien - 6.
questions in the performance of the agency's duty. (See
Peterson V. Board of Trustees of the Firemen's Pension Fund of
the City of Des Plaines (1973), 54 Ill. 2d 260, 262-63; Dunn V.
Director, Department of Labor (1985), 131 Ill. App. 3d 171,
173.) Accordingly, it is my opinion that under section 5-12 of
the Public Community College Act, the Capital Development Board
may determine whether building defects in a community college
building are the result of design error or defective construction even though a lawsuit resulting from such building defects
has been settled and that settlement effectively works to
preclude a judicial determination on causation or fault
regarding the building defects.
As to your second question, it is my opinion that,
under the factual circumstances you have presented, the release
executed by Sauk Valley College and the IBA in the course of
settling the claim or claims emanating from the building
defects in question does not preclude the CDB from using State
funds to correct the defects pursuant to section 5-12 of the
Public Community College Act.
As stated above, section 5-12 imposes a duty upon a
community college which receives funding under section 5-12 to
reimburse the State if the college recovers damages against the
party responsible for the defects. Moreover, it may reasonably
be contended that the CDB acquires a right of subrogation from
Gary J. Skoien - 7.
the college when it provides funding to correct building
defects under section 5-12. (See generally 83 C.J.S. Subrogation § 1 et seq. (1953); 34 I.L.P. Subrogation § 1 et seq.
(1958) ) A release, however, extinguishes and discharges its
subject claims and bars or prevents any further action
thereon. (Touhy V. Twentieth Century-Fox Film Corp. (1979), 69
Ill. App. 3d 508, 512; Smith V. Lehn & Fink Products Corp.
(1977), 46 Ill. App. 3d 1002, 1009.) Since a party with the
right of subrogation, i.e., a subrogee, has no greater rights
than the subrogor and can enforce only the rights of the
subrogor (McCormick V. Zander Reum Co. (1962), 25 Ill. 2d 241,
244; blume V. Evans Fur Co. (1984), 126 Ill. App. 3d 52, 54),
the general rule is that a release executed by the subrogor in
favor of the original obligor without the consent of the
subrogee destroys the right of subrogation and relieves the
subrogee from paying on the claim or debt to the same extent
that the original obligor is relieved. (See generally McHenry
State Bank V. Y & A Trucking, Inc. (1983), 117 Ill. App. 3d
629, 633; Grundy County National Bank V. Cavanaugh (1982), 105
Ill. App. 3d 718, 721; Cak brook Bank V. Hawthorne Bank of
Wheaton (1980), 90 Ill. App. 3d 642, 647; Aupperle & Sons, Inc.
V. American Indemnity Co. (1979), 75 Ill. App. 3d 722, 724;
Priess V. Buchsbaum (1947), 332 Ill. App. 565, 574-75.) Assum-
ing arguendo that the CDB possesses a right of subrogation for
Gary J. Skoien - E.
providing funds to remedy building defects in a community
college building, the release of the parties responsible for
the defects without the consent of the CDB could serve to
relieve the CDb from funding the corrective work. Such action
also adversely affects the CDB's statutory right to reimburse-
ment since no action can be instituted to recover damages.
Under the factual circumstances you have presented, however, it
appears that the CDB may not now rely upon the College's
release of the parties allegedly responsible for the building
defects to escape its responsibility to fund the work to
rectify the defects.
As you know, pursuant to section 10.01A of the Capital
Development board Act (Ill. Rev. Stat. 1983, ch. 127, par.
780.01A), the CDB is the successor agency to the IBA, and all
the powers, functions and duties of the IBA have been trans-
ferred to the CDB. As the successor to the IBA, the CDb stands
in the place of the IEA, and therefore, the actions of the IBA
essentially have become the actions of the CDB with respect to
the subject College building. You have advised that the IbA
consented to the release of the building A/E and contractor by
the College by participating and jointly releasing those
parties in the course of settling the lawsuit. Consequently,
the release by the IEA constitutes release by the CDB as the
successor to the IBA. Accordingly, the CDB will be estopped
Gary J. Skoien - 9.
from claiming that its rights have been adversely affected by
the release. Therefore, it is my opinion that, under the facts
you have provided, the release does not preclude the CDB from
using State funds, pursuant to section 5-12 of the Public
Community College Act, to correct building defects in the
community college building which are the result of design error
or defective construction.
Ver truly yours,
AT TORNEY GENERAL