32 Ill. Adm. Code 370.50
Requirements for Certification
Section 370
Section 370.50 Requirements
for Certification
a) Except as otherwise provided in subsection (b)(1)(C) and
Section 370.40, a certificate issued by the Agency is required for lawful
operation of all mammography facilities subject to the provisions of this Part.
Facilities performing mammography shall meet the requirements of Sections
370.70, 370.80, 370.90, 370.100, 370.110, 370.120 and 370.130 and be accredited
by an FDA-approved accreditation body. Each mammography unit shall be
accredited by or have an application pending for accreditation with an FDA-approved
accrediting body.
AGENCY NOTE: Currently, the only FDA-approved accrediting
body in Illinois is the American College of Radiology.
AGENCY NOTE: Except for provisional certificates and interim
notices, the term of certificates issued under this Section shall be for 3
years.
b) Application.
1) Certificates.
A) In order to qualify for a certificate, a facility shall apply
to an accreditation body.
B) Following the Agency's receipt of the accreditation body's
decision to accredit a facility, the Agency may issue a certificate to the
facility, or renew an existing certificate, if the Agency determines that the
facility has satisfied the requirements for certification or recertification.
C) An interim notice authorizes the facility to perform
mammography until the facility receives its certificate but in no case for more
than 45 days. No more than one interim notice may be issued to a facility per
application for certification. The Agency may issue an interim notice of
mammography certification by facsimile to a facility if a delay is anticipated
in providing a certificate to the facility under one or more of the following
circumstances:
i) The Agency has been notified by an accreditation body that
the facility meets the requirements for a provisional or provisional
reinstatement certificate and delivery of the certificate may take more than 24
hours;
ii) The Agency has been notified by an accreditation body that
the facility has completed accreditation or reaccreditation and delivery of the
certificate to the facility may take more than 24 hours; or
iii) The Agency has been notified by an accreditation body that
the facility has timely submitted an application for accreditation or
reaccreditation but the completion of the accreditation process may extend
beyond the expiration date of a facility's existing certificate through no
fault of the facility.
2) Provisional certificates. A new facility is eligible to apply
for a provisional certificate. The provisional certificate will enable the
facility to perform mammography and to obtain the clinical images needed to
complete the accreditation process.
A) To receive a provisional certificate, a facility shall apply
and submit the required information to an FDA-approved accreditation body.
B) Following the Agency's receipt of the accreditation body's
decision that a facility has submitted the required information, the Agency may
issue a provisional certificate to a facility upon determination that the
facility has satisfied the requirements for provisional certification. A
provisional certificate shall be effective for up to 6 months from the date of
issuance. A provisional certificate cannot be renewed, but a facility may
apply for a 90 day extension of the provisional certificate.
C) In the event the facility is denied accreditation by the
accrediting body with time remaining on the provisional certificate, the
provisional certificate expires immediately with the denial and the facility
must stop performing mammography.
3) Extension of provisional certificate.
A) To apply for a 90 day extension to a provisional certificate, a
facility shall submit to its accreditation body a statement of what the
facility is doing to obtain certification and evidence that there would be a
significant adverse impact on access to mammography in the geographic area
served if such facility did not obtain an extension.
B) Following the Agency's receipt of the accreditation body's
decision that a facility has submitted the required information, the Agency may
issue a 90 day extension of the provisional certificate to the facility upon
determination that the facility has satisfied the requirements for the 90 day
extension.
C) There can be no renewal of a provisional certificate beyond the
90-day extension.
c) Reinstatement policy. A previously certified facility that
has allowed its certificate to expire, that has been refused a renewal of its
certificate by FDA or the Agency, or that has had its certificate suspended or
revoked by FDA or the Agency, may apply for reinstatement. If reinstated, the
facility will be eligible for a provisional certificate.
1) Unless prohibited from reinstatement under subsection (c)(4),
a facility applying for reinstatement shall:
A) Contact an FDA-approved accreditation body to determine the
requirements for reapplication for accreditation;
B) Fully document its history as a previously provisionally
certified or certified mammography facility, including the following
information:
i) Name and address of the facility under which it was
previously provisionally certified or certified;
ii) Name of previous owner/lessor;
iii) Facility identification number assigned to the facility under
its previous certification; and
iv) Expiration date of the most recent provisional certificate or
certificate; and
C) Justify application for reinstatement of accreditation by
submitting to the accreditation body a corrective action plan that details how
the facility has corrected deficiencies that contributed to the lapse, denial
of renewal or revocation of its certificate.
2) The Agency may issue a provisional certificate to a previously
certified facility:
A) Following the Agency's receipt of the accreditation body's
decision that a facility has adequately corrected, or is in the process of
correcting, pertinent deficiencies at the facility; and
B) The Agency determines that the facility has taken sufficient
corrective action since the lapse, denial of renewal or revocation of its
previous certificate.
3) After receiving the provisional certificate, the facility may
lawfully resume performing mammography services while completing the
requirements for certification.
4) If a facility's certificate was revoked on the basis of an act
described in Section 370.160, no person who owned or operated that facility at
the time the act occurred may own or operate a mammography facility within 2
years after the date of revocation.
d) Appeals of adverse accreditation or reaccreditation
decisions. The appeals procedures described in this subsection (d) are
available only for adverse accreditation or reaccreditation decisions that
preclude certification or recertification by the Agency.
1) Upon learning that a facility has failed to become accredited
or reaccredited, the Agency will notify the facility that the Agency is unable
to certify that facility without proof of accreditation.
2) A facility that has been denied accreditation or
reaccreditation is entitled to an appeals process from the accreditation body.
A facility shall avail itself of the accreditation body's appeal process before
appealing that decision to the FDA.
3) In the event that a facility, after availing itself of the
accreditation body's appeal process, receives an adverse accreditation or
reaccreditation decision, the facility may appeal that decision to the FDA. In
order to appeal, the facility shall send a request for reconsideration to the
FDA