32 Ill. Adm. Code 505.1200
Inspection Certificates
Section 505
Section 505.1200 Inspection
Certificates
This Section is not intended to
be, in any way, inconsistent with the applicable regulations, rules and
requirements of the NRC. If a requirement of this Section as applied in any
situation is or would be inconsistent with the regulations, rules and requirements
of the NRC, the requirements of this Section shall not be applied. The Agency
will take action in regard to an Inspection Certificate only in accordance with
Section 505.80. The Agency shall issue Inspection Certificates for nuclear
power systems in accordance with this Section if the reports, programs and
plans required to be submitted by this Section, Sections 505.110 and 505.1100
are submitted in accordance with the frequencies and standards specified in
those Sections and are in compliance with this Part.
a) Owners of nuclear power systems shall not operate those
nuclear power systems without a valid Inspection Certificate issued by the Agency.
The Agency shall issue one Inspection Certificate for each nuclear power system
at a nuclear facility. Unless suspended by the Agency, the Inspection
Certificate shall remain valid through the 6-month period following the end of
the inservice inspection period for which the certificate was issued, or as
otherwise permitted by this Part.
b) Owners of nuclear power systems not yet in operation shall,
prior to operation of the nuclear power systems, have a valid Inspection
Certificate issued by the Agency for the nuclear power systems. The Agency
shall issue the initial Inspection Certificates for the first inservice
inspection period based on an Agency determination that the submittal
requirements of Section 505.1100 are met.
c) An Inspection Certificate shall be issued for each nuclear
power system at the nuclear facility for the succeeding inservice inspection
period when the Agency determines that:
1) The examinations and tests required by the Inservice
Inspection Plan during the preceding inservice inspection period were
completed; and
2) All related submittal requirements of this Part are met.
AGENCY NOTE:
In order to determine whether the examinations and tests required by the
Inservice Inspection Plan during the preceding inspection period were performed
and completed, the Agency will review the submittals required by this Section
against the Inservice Inspection Plan and the applicable edition and addenda of
the ASME Code Section XI. The review and determination will be made separately
for each nuclear power system. During this review the Agency shall accept
requests for relief from ASME Code Section XI requirements that have been
approved by the NRC.
d) The inservice inspection interval for the nuclear power system
may be extended or reduced as permitted by the applicable Code edition and
addenda or that has been approved by the NRC. The owner shall notify the Agency
in writing of any such change in the inservice inspection interval. The Agency
may issue a new Inspection Certificate, or may adjust the term of the
Inspection Certificate in effect for the applicable inservice inspection period.
e) When the owner discovers that an ISI boiler or pressure vessel
is not in compliance with this Part, the owner shall take measures to bring the
ISI boiler or pressure vessel into compliance. Those measures may include, but
are not limited to, repair or replacement of the ISI boiler or pressure vessel
in accordance with Section 505.1500. In such cases, the owner shall notify the
Agency in accordance with Section 505.140. The owner shall submit information
concerning the details of the noncompliance and the measures taken to bring the
noncomplying ISI boiler or pressure vessel into compliance to the Agency within
90 days following the completion of the corrective measures. Any replacement
ISI boiler or pressure vessel shall meet the requirements of this Part for new
boilers and pressure vessels and shall be registered by the owner with the Agency
in accordance with Section 505.1100. The Agency shall review the information
submitted regarding the noncompliance and the corrective measures taken and may
issue a revised Inspection Certificate to reflect any change in nuclear power
system composition.
f) The owner shall submit the following:
1) In addition to the information submitted under Section
505.1100, the owner shall submit to the Agency within 90 days after completing a
refueling outage:
A) The inservice inspection summary report required by ASME Code
Section XI;
B) The Owner's Data Report, form NIS-1, required by ASME Code
Section XI or an equivalent form;
C) The Owner's Report for Repairs or Replacements, form NIS-2 of
Section XI or an equivalent form, if required by the applicable Code Edition
and Addenda or Code Case used, for all repairs and replacements performed since
the last inservice inspection; and
D) Deviations from the Inservice Inspection Plan implemented
during inservice inspections that impact upon compliance with this Part.
2) The owner shall submit the Inservice Inspection Plan for the
next inservice inspection interval to the Agency prior to the end of each
inservice inspection interval.
g) The Agency shall take action under Section 505.80 if the Agency
finds that:
1) The submittals in subsection (f) have not been made or are
incomplete; or
2) The examinations and tests required by the owner's Inservice
Inspection Plan have not been performed or are incomplete; or
3) The owner has not met the requirements of subsection (e); or
4) The nuclear power system is not being inspected in accordance
with this Part.
h) In addition to the requirements of this Section, owners shall
meet the requirements of Section 505.120.